Schedule of values

Definition

A schedule of values is an itemized breakdown of a construction contract's total price into individual parts of the work, each with its own dollar value. Agreed before the project starts, it becomes the basis for progress billing: each period, the contractor bills the percentage of each line completed.

Also called: SOV, Cost breakdown

Create your first invoice in minutes.

Free to start, no card required.

Create a Free Invoice →

Schedule of values in practice

Lines usually follow trades or phases, such as mobilization, site work, foundations, framing, electrical, plumbing, and finishes. The values must add up to the contract sum, and approved change orders are added as new lines.

Balance the values honestly. Owners and lenders watch for "front-loading", where early items are overvalued so the contractor is paid ahead of the work, and may reject a schedule that looks unbalanced.

A clear schedule of values makes each pay application easy to check and reduces disputes over how much of the work is really done.

Example

A $150,000 remodel has a schedule of values with seven lines, including demolition $12,000, framing $28,000, and electrical $22,000. When electrical is half done, the next pay application bills $11,000 for that line.

Frequently Asked Questions

Who prepares the schedule of values?

The contractor usually prepares it and submits it for approval by the owner or architect before the first pay application.

Can the schedule of values change during a project?

Approved change orders are added as new lines. Moving value between existing lines generally needs the owner's agreement.

Related terms

This page is for general information only and is not legal, tax, or financial advice. Rules change and vary by location, so consult a qualified lawyer or accountant about your situation.

Invoice Website

Put the term to work.

Create a professional invoice or estimate in minutes. Free to start, no card required.